Which of the following statements regarding CPM networks is true? A. There can be multiple critical paths on the same project

Also Check This  ¿Qué significa “Soplame la vela”?

Answer

Answer : B. If a specific project has multiple critical paths,
all of them will have the same duration.

Note : In case of large or complex projects there can be
multiple critical paths which are grouped in more than one sequence
while the duration for all the critical path remains similar.